LAKE WHITNEY RANCH DEVELOPMENT
BATHHOUSE 1MAKE A DONATION |
BATHHOUSE 2 LWR GOAL Four bathhouses $250,000 each 5KRUN WALK |
GET INVOLVED DEVELOPMENT SCHEDULEINFRASTRUCTURE: Bathhouses/Shower Houses and RV's Site: Underground pipes by gravity to the wastewater treatment plants will by done by March 11. ----------------------------------------------------- Bathhouses /Shower House Pads: Pads are scheduled to be done before April 14. ----------------------------------------------------- Bathhouses/Shower House Buildings Construction bid process. Final date is March 16 ----------------------------------------------------- "Update Videos". |